Fire Department Project Update – August/September 2021
Schedule: Substantial Completion was achieved on August 3, 2021. Concerns/Issues: Ceiling occupancy/vacancy sensors in various areas are not working. Attic stairway light not dimming. Apparatus Bay lighting goes into emergency mode when shut off. Apparatus Bay floors showing tire marks.
Read moreFire Department Project Update – July 2021
Demolition: Demolition and abatement work is complete. Concrete: Concrete work is complete. Masonry: The lead flashing at the front entrance roof and the cornice returns were completed. Metals: Miscellaneous Metals work is complete. Caulking :Interior caulking at the apparatus bay
Read moreFire Department Project Update – June 2021
Masonry: Brickwork restoration, replacement and re-pointing is complete. The stone veneer at the retaining wall is complete. The brick sills at the front of the station were replaced. Roofing: Gutter and sheet metal work is ongoing. The zinc coated plumbing
Read moreFire Department Project Update – May 2021
Weather: Weather was favorable for construction. No time was lost to unseasonable weather this month. Demolition: Phase 2 Demolition and Hazardous Waste Remediation was completed. Selective Demolition of the administration side and apparatus bay was completed. Cast-in-Place Concrete: Front apron
Read moreFire Department Project Update – April 2021
Demolition: Phase 2 demolition and hazardous waste abatement is ongoing. The Apparatus Bay doors on Main Street were removed and replaced. Cast-in-Place Concrete: Dumpster pad and Tight Tank Apron were formed and placed. Masonry: Brick veneer was installed at the
Read moreFire Department Project Update – March 2021
Cast-in-Place Concrete: Concrete landings were placed at the Southside Addition, the Rear Vestibules, and the Apparatus Building. Equipment pads were placed for the AC Condenser, Compressor, and the Water Heater. Masonry: Brick Veneer installation which began this week is ongoing.
Read moreFire Department Project Update – February 2021
In February 2021 the committee brought an article to Special Town Meeting refunding the monies for Fagan Drive costs from the Stabilization account in the amount of $312,683. The article also called for using $700,000 from the Stabilization fund in
Read moreFire Department Project Update – January 2021
Site and Earthwork: The storm water infiltration basin and sediment forebays were cut and filled. The infiltration basin’s overflow was piped to the manhole on Butler Ave and loose laid stone was placed on the embankment at the southeast property
Read moreFire Department Project Update – December 2020
Site and Earthwork: Site Work is ongoing. Structural fill from TL Edwards was tested and approved and used as a base for the asphalt paving. Asphalt base was applied to the driveways. ATC was onsite to test temperature and compaction.